14 milestones · 1 passed · 13 upcoming

2026-05-27T-14 weeks
✓ passed

Planning kickoff — Master Project Plan locked, sponsor outreach groundwork, lineup longlist underway.

2026-06-13T-12 weeks
in 4d

Brand finalized. Sponsor deck ready. Vendor applications open. Lineup longlist complete. Budget v1 done.

2026-06-27T-10 weeks
in 18d

Permit and noise exemption applications submitted. Insurance quotes received. Anchor sponsor conversations live.

2026-06-30T-9.5 weeks
in 21d

Upington Fire & Rescue consultation complete (SM-001). Insurance carrier FR requirements confirmed (CL-004).

2026-07-11T-8 weeks
in 32d

Lineup confirmed. Vendor selection complete. Major supplier quotes in. POPIA review complete.

2026-07-25T-6 weeks
in 46d

HARD LOCK — Fire treatment route decided (SM-002). Sponsor contracts signed. Insurance bound. Worship service team confirmed.

2026-08-08T-4 weeks
in 60d

All artist contracts and technical riders in. Site build schedule locked. All supplier contracts signed.

2026-08-22T-2 weeks
in 74d

Site build prep complete. FR-treated hay bales ready. Staff and volunteer briefings done.

2026-09-01T-3 days
in 84d

Site build complete. Fire department sign-off. Final walkthrough.

2026-09-04EVENT DAY 1
in 87d

Vlam Fees opens — Friday 19:00.

2026-09-05EVENT DAY 2
in 88d

Main festival day.

2026-09-06EVENT DAY 3
in 89d

Worship service opens. Closes 16:00.

2026-09-30T+3 weeks
in 113d

Financial reconciliation complete. Sponsor wrap-up reports delivered.

2026-10-15T+5 weeks
in 128d

Lessons learned doc complete. Year-2 brief drafted.